Michigan’s Line 5 tunnel permits are frozen for now. Gov. Gretchen Whitmer said on Tuesday, Nov. 24, that she had told the Department of Environment, Great Lakes and Energy to stop processing the remaining state approvals for a proposed tunnel beneath the Straits of Mackinac, pending resolution of legal questions left open by the Michigan Supreme Court.
The order touches Line 5 tunnel permits only. It halts paperwork rather than oil flow: the pipeline keeps operating and the project has not been cancelled.
Line 5 Tunnel Permits Pause Follows a Summer Court Ruling
The pipeline runs 645 miles from northwestern Wisconsin to southwestern Ontario. Along that route, a 4.5-mile twin span rests directly on the bed of the Straits, the waterway joining Lake Michigan and Lake Huron, as Planet Detroit and Michigan Advance both described.
In late July, the Michigan Supreme Court told the Michigan Public Service Commission, the body that regulates utilities, to take another look at the approval it had granted for the tunnel. The justices concluded the commission had not given adequate weight to the environmental consequences of keeping the pipeline in service for decades longer.
Whitmer then asked EGLE in September to assess what that ruling meant for the department’s own Line 5 tunnel permits. Tuesday’s order went further, converting that review into a standstill.
EGLE spokesperson Scott Dean confirmed the pause. In a statement, the department said that holding off until the legal picture clears was the right course for the lakes, for natural resources and for the communities whose livelihoods rest on them.
Enbridge Calls the Ruling a Revocation While Two Outlets Call It a Remand
The record is less tidy than it first appears. Planet Detroit and Michigan Advance both describe the July decision as an order sending the matter back to the commission. Michigan Public frames it as a finding that the state had not adequately assessed environmental effects, returning the project to regulators.
Enbridge, which owns the line, used stronger language. A company statement referred to the court’s “recent decision to revoke the Michigan Public Service Commission approval” and said it had introduced new uncertainty. Whitmer, for her part, said the ruling brings significant delay and uncertainty.
According to Michigan Public, the company will have to file a fresh application with the commission. That procedural step, rather than any shutdown order, is what the state is now waiting on.

Two Contested Cases Filed and One Discharge Permit Still Undecided
Opponents moved quickly. Two separate requests for a contested case were filed over the package of Line 5 tunnel permits EGLE granted in July, with the filings arguing that the tunnel would endanger the environment and the cultural resources and lifeways of tribal nations in the region.
Still unresolved is a National Pollution Discharge Elimination System permit. It would let Enbridge release as much as 6 million gallons of construction wastewater into the Great Lakes after treatment at one of two sites at opposite ends of the Straits.
No schedule has been published for deciding that application or the two contested cases. As of Nov. 24, EGLE had not indicated when it would act.
Enbridge Points to Its Review Record as a Tribal Leader Warns of More Action
Enbridge spokesperson Ryan Duffy said the state issued Line 5 tunnel permits in July 2026 and earlier in 2021, and that each round involved technical review, public meetings and hearings, thousands of public comments and extensive engagement with tribal leaders and state agencies.
In comments to Michigan Public, the company also argued that the pipeline supplies energy residents of Michigan and the Great Lakes region rely on daily. The outlet discloses in an editor’s note that Enbridge is among its corporate sponsors.
Whitney Gravelle, president of the Bay Mills Indian Community, said the pause settles nothing. “This decision is not the finish line,” she said, according to Planet Detroit.
What Remains Approved and What the Freeze Does Not Touch
The suspension of Line 5 tunnel permits covers EGLE’s pending work only. Michigan Public reported that the U.S. Army Corps of Engineers had already cleared the tunnel, and that the Department of Natural Resources and EGLE had approved it in earlier rounds.
Whitmer tied the announcement to a position she has held since 2020, when she called for the Straits segment to be shut down. She has said repeatedly that her goal is to get the pipeline out of the water, warning that a single spill would threaten the state’s water, economy and way of life.